Tip of the Month: Project Schedule Do’s and Don’ts

timeline photo

Tip of the Month:
Project Schedule Do’s and Don’ts -DO use Hard Logic and Soft Logic when assigning predecessors and successors:

o Hard Logic: Tasks MUST be completed before the successor task can start; example, Task A MUST be completed before Task B can start

o Soft Logic: Tasks can be worked in any order, but MUST be related to another task; example, Task A or Task B can be scheduled in any order, but MUST be related to other existing tasks